6 posts tagged with "Goals"

View All Tags

· One min read

From: 28/11/2022

To: 18/12/2022

Scrum Master: João Reis Product Owner: João Farias

Developers: Artur Romão, Mariana Rosa, Ricardo Rodriguez

Sprint Planning

These sprint will be the final sprint.

User story:

  • As Alexandre, I want to store CCTV footage of the intrusion, so that I can use that information as legal proof and serve it to the client (13 story points)

  • As Alexandre, I want to know my clients information, so that I can be in contact with them whenever I need. (3 story points)

The goals will be:

  • Connect everything (AWS) and deploy them;
  • More focus on documentation;
  • Fix some bugs;

Story Points Estimated: 16

Sprint Review

This sprint was the best until this point. The team worked really well to delivery to the stakeholders what they wanted. The stakeholders gave a positive review.

Story Points Delivered: 16

Sprint Retrospective

  • What went well? The sprint itself, the team was really focused and motivated to delivery the User Stories

  • What could be improved? Nothing.

  • What went badly? A lot of AWS problems, in the next sprint we will try other solutions.

Burndown Chart

Burndown Chart of sprint 5

· 2 min read

From: 14/11/2022

To: 28/11/2022

Scrum Master: Ricardo Rodriguez

Product Owner: João Farias

Developers: Artur Romão, João Reis, Mariana Rosa

Sprint Planning

In these sprint the group will focus on these two User Stories:

  • As Alexandre, I want to be responsible for adding the cameras and sensors that were installed into the system so that a new client that wants to protect his new business can be satisfied. (2 points)

  • As Teresa, I want to login in my account, so that I can access my dashboard (2 points)

  • As Teresa, I want to store CCTV footage of the intrusion, so that I can use that information as legal proof the moment I make a complaint to the police. (2 points)

  • As Teresa, I want the light and sound alarms to be automatically triggered, if an intrusion is detected, so that I can keep my business safe and avoid robberies. (2 points)

In the fourth sprint we were expecting to complete the following user story from the previous sprint: "As Teresa, I want to be notified when an intrusion occurs in my business, so that I can allow myself to be more comfortable and feel safe about my investment."

To do so we need to have this Sprint Goals:

  • IDP Login
  • Add properties, cameras, sensors on the dashboard Client and Manager UI
  • Trigger these equipments in case of intrusion
  • Deploy Microservices

Story Points Estimated: 8

Sprint Review

This sprint was the best until this point. The team worked really well to delivery to the stakeholders what they wanted. The stakeholders gave a positive review.

Story Points Delivered: 8

Sprint Retrospective

  • What went well? The sprint itself, the team was really focused and motivated to delivery the User Stories

  • What could be improved? Nothing.

  • What went badly? A lot of AWS problems, in the next sprint we will try other solutions.

Burndown Chart

Burndown Chart of sprint 4

· 2 min read

From: 1/11/2022

To: 13/11/2022

Scrum Master: Mariana Rosa

Product Owner: Ricardo Rodriguez

Developers: Artur Romão, João Farias, João Reis

Sprint Planning

In the third sprint we were expecting to complete the following user story from the previous sprint: "As Teresa, I want to be notified when an intrusion occurs in my business, so that I can allow myself to be more comfortable and feel safe about my investment." (5 points)

To do so we need to have this Sprint Goals:

  • To Finish API Sites Management
  • Store Intrusions in DataBase, when HDM detects it
  • Intrusion API communicate with Notifications API, through API Gateway
  • Intrusion API asks for video frames to camera API and this module answers through rabbit mq
  • Intrusion API joins the received frames in a video and send it to AWS S3.

Story Points Estimated: 5

Sprint Review

This sprint was not one of the bests, multiple reasons why. However, the fact that the API Sites Management was practically done was a great thing and the two API can already communicate and send video to AWS.

Story Points Delivered: 0

Sprint Retrospective

  • What went well? Important goals reached.

  • What could be improved? Better time management.

  • What went badly? The team had a lot of other work from other courses.

Burndown Chart

Burndown Chart of sprint 3

· One min read

From: 24/10/2022

To: 31/10/2022

Scrum Master: Artur Romão

Product Owner: Mariana Rosa

Developers: João Farias, João Reis, Ricardo Rodriguez

Sprint Planning

In the third sprint we were expecting to achieve these goals:

  • User story 1: As Teresa, I want to login in my account, so that I can access my dashboard; (3 points)
  • User story 2: "As Teresa, I want to be notified when an intrusion occurs in my business, so that I can allow myself to be more comfortable and feel safe about my investment." (5 points)
  • Focus more on the client side and backend;
  • Communication flow between Camera API, Intrusion API and HDM;
  • Client UI with access to create and login account (without IDP yet), check his intrusions and profile page.

Story Points Estimated: 8

Sprint Review

Stakeholders appreciated that we were delivering user stories, however we need to be more efficient.

Story Points Delivered: 3

Sprint Retrospective

  • What went well? Client side pretty much developed.

  • What could be improved? Even the work in the team.

  • What went badly? Nothing serious.

Burndown Chart

Burndown Chart of sprint 2

· 2 min read

From: 17/10/2022

To: 24/10/2022

Scrum Master: João Reis

Product Owner: João Farias

Developers: Artur Romão, João Farias, Mariana Rosa

Sprint Planning

In our second week of development, the actual first sprint, the goals are the following:

  • User story: "As Teresa, I want to check on my property's information" (3 points)
  • Develop client's frontend
  • Build Site's Management API
  • Connect the two modules in order to present information to client, such as, their properties, the intrusion's history and the devices present in their properties.

Story Points Estimated: 3

Sprint Review

Although, frontend was developed successfully, unfortunately backend module wasn't. Our modulation suffered some changes during the sprint, and we had to modulate our backend module several times which made us lost a bit of time. However, 2 of 3 goals where accomplished and the user story was delivered.

Story Points Delivered: 3

Sprint Retrospective

  • What went well? We improved from the previous sprint by splitting the tasks into smaller ones and work towards one goal together

  • What could be improved? More communication between the team, we had some problems because of that.

  • What went badly? Nothing serious.

Burndown Chart

Burndown Chart of sprint 1

· 2 min read

From: 10/10/2022

To: 17/10/2022

Scrum Master: João Farias

Product Owner: João Reis

Developers: Artur Romão, Mariana Rosa, Ricardo Rodriguez

Sprint Planning

In order to start our project, it is expectable to conclude the following sprint goals:

  • Configure the GitHub organization and define the Git Workflow.
  • Create User Stories, Personas
  • Produce a functional frontend prototype for the sites management API with some working features.
  • Define, document and test the most important endpoints of the intrusion management API.
  • Implement the database for the sites management API.
  • Implement CI/CD for at least one of the system modules.

Story Points: 0

Sprint Review

After the sprint review, the stakeholders advise us to take "baby steps". Our goals were too general and difficult, we should focus on the user stories. Work in a vertical way, which means, every member of the team is focused on that goal and work in all the modules (Backend, Frontend, Testing, DevOps) to deliver user stories. 3 of the goals were accomplished.

Sprint Retrospective

  • What went well? We have all now to start working (user stories prioritized, documentation, frontend prototype and the Sites Management API)

  • What could be improved? Less big goals.

  • What went badly? For the next sprint, we will try to go more focused in something smaller.

Burndown Chart

Burndown Chart of sprint 0